What’s required to reach “full-approval” phase?

The comprehensive list of information is adapted based on specific market conditions. In general, we require that the energy customer provides us with up-to-date financial statements as well as a declaration that he is not being pursued by the law for unpaid debts. We also need to attest to the local consumption by checking the electricity bills of the past two years. Technically, we require detailed engineering designs with full material specifications as well as a formal site surveying report. A construction permit, when required, must be obtained as well as a connection permit.